CEQ’s General Construction Division was tasked with the electrical design, installation and commissioning for the upgrade of the existing QR Mayne facility at Bowen Hills, Brisbane.

The works included installation of new 1500kVA Transformer, 4 new distribution boards, upgrades to the lighting, power, fire and emergency lighting throughout 2 buildings and a new service platform for the safe access and egress of the rolling stock. The complex program of works required CEQ to demonstrate flexibility whilst completing each section and work closely with QR Staff.

The team performed all works whilst maintaining access to the QR employees to allow a seamless integration between the remaining service facility and the new installation.